Resource Rent Tax Misconceptions

WAYNE MAYO


A 'pure' cash flow tax on investments would see negative cash flow (revenue from investment less than the associated capital plus operating costs) either attract an immediate (or delayed) government cash rebate equal to the cash flow loss times the tax rate or able to be sold to others who have positive cash flow - that is, 'full loss offset' would apply. Symmetrically, tax would be paid on positive cash flow (revenue greater than associated costs).

A resource rent tax (RRT) is a variant of cash flow taxation that involves cash flow losses being carried forward with interest to be offset against future positive cash flow rather than attracting government cash rebates. Like cash flow taxation, an RRT seeks to tax above normal profits (from whatever source) and to have minimal effect on investment decisions - though the absence of government cash rebates means there is a risk of the value of losses never being recouped.

The Australian Government introduced an RRT to apply to offshore 'greenfields' petroleum projects from 1 July 1984 - the Petroleum Resource Rent Tax (PRRT). In May 2010, the Australian Government proposed the application of a tax, called the Resource Super profits Tax (RSPT), to all mining and petroleum operations in Australia (except those subject to the PRRT). By incorporating delayed full loss offset, the RSPT was financially equivalent to a cash flow tax. After a period of consultation, the Government proposed in July 2010 revised arrangements involving: an RRT to apply to the mining of iron ore and coal in Australia - the Minerals Resource Rent Tax (MRRT); and, extension of the PRRT to all Australian onshore and offshore oil and gas projects.

This paper looks at a number of common misconceptions concerning the design of an RRT.


1. An RRT is complex
2. Loss carry-forward with interest (threshold rate) is the basis of an RRT
3. Loss carry-forward with interest is only relevant to an RRT
4. Threshold rate for loss carry-forward should be based on characteristic level of risk in associated industry
5. The threshold (or uplift) rate defines what economic rent (or excess profits) an RRT taxes
6. The interrelationship between RRT (or cash flow taxes generally) and income taxation raises no special issues
7. Hedging should be excluded from an RRT

MISCONCEPTION 1: AN RRT IS COMPLEX

Some people, familiar with income tax laws, view resource rent taxes as unusual and complex. An RRT is, however, not complex at all. At its core it is a simple cash flow tax. Cash outflow on activities subject to an RRT is immediately deductible. Revenue from the activities is immediately assessable. Cash outflow might be for capital expenditure on assets (producing revenue streams beyond the year of expenditure) or for regular annual operating costs. Figure 1 illustrates early deductible capital expenditures (start and end of Year 1) on a project subject to an RRT and the later assessable net receipts (gross revenue less operating costs) flowing from those capital expenditures.

Stylised crude oil project before RRT

Income taxation requires a decision to be made over whether an item of expenditure either:

With change in value of assets included in the income tax base (for a bank account, this change in value is 'interest' on the account), pre-tax returns are reduced by the tax. For an asset that is 'marginal', or only just commercially viable (absent risk, producing returns that could be got from a bank account), its pre-tax return is reduced by income taxation neatly in proportion to the investor's income tax rate if the annual change in value of the asset is relected in the investor's income tax assessment (as is the case with bank interest). Thus, investors' discount rate (what interest rate the investor can alternatively get from financial markets) is reduced by income taxation. How neutral income tax arrangements are on investment decisions depends importantly on how closely change in value of assets (and liabilities) is reflected in investors' income tax assessments.

In contrast, an RRT involves no such complexities. Under an RRT: cash flow out, immediately deductible; cash flow in, immediately assessable. With an RRT therefore where capital expenditure in a year can be written off against positive RRT cash flow, the after-RRT outlay on capital expenditure is reduced by a proportion equal to the RRT tax rate. Similarly, positive annual net receipts (gross revenue less annual operating costs) flowing from a taxpayer's RRT assets are also reduced by a proportion equal to the RRT tax rate. Thus, in these circumstances, the after-tax outlay on capital expenditure in any year is reduced (through immediate write-off) by the same proportion (the tax rate) that ensuing annual net receipts are reduced by tax payments. In Figure 1, if the RRT tax rate were 50%, the capital expenditures in at start and end of Year 1 would be reduced by half by the RRT, as would the net receipts in Years 2, 3 and 4.

In such circumstances where all pre-tax cash flow is reduced in proportion to the RRT tax rate, pre-tax return of the project in Figure 1 would be the same post-RRT. To illustrate further, take a very simple example where $100 is invested at start Year 1 to get $106 at end Year 1. The pre-tax return of this investment is 6% pa. If, under an RRT with a 50% tax rate, the $100 outlay could be written off immediately against other RRT income, the post-RRT cash flow would become $50 at start Year 1 to get $53 at end Year 1 (with the $106 taxed at 50%). Post-RRT, the investment still has a 6% pa return. Thus, unlike the situation with income taxation, the investor's discount rate is unchanged by an RRT when negative cash flow can be immediately offset against other RRT income.

An RRT could be designed to apply to to all the cash flows of an investment project, including financing flows. Unchanged return given the same proportional reduction in pre-tax cash flow applies equivalently to liabilities as to assets. Design of RRT is, however, usually discussed in terms of exclusion of interest from the RRT tax base (contrasting income taxation which includes interest in its base). More specifically, cash flows associated with any borrowing (or capital raising generally) or lending are usually excluded from design of an RRT. Under this design, When analysing investments subject to an RRT it is cash flows associated with return on total investment that are involved, not those associated with returns on equity investment.

Viewed from this traditional RRT design, some may construe exclusion of interest from the RRT base as the underlying reason an RRT does not affect an investor's discount rate - with that unchanged discount rate, in turn, requiring capital expenditure to be immediately expensed for the achievement of investment neutrality. That explanation then nicely contrasts the parallel explanation with income taxation which says that because interest is included in the tax base, the investor's pre-tax discount rate is changed and with that change the treatment of capital expenditure required for neutrality changes from immediate write-off under the RRT to annual change in value of assets under income taxation.

Typically, an investment project involves a stream of capital expenditures (resulting in negative annual cash flow) in the early years followed by positive cash flows over ensuing years. Net present value, NPV, is the sum of all the positive and negative cash flows of a project brought together in dollars of the same point in time – say, the start of the investment project or the ‘present’. A specified interest, or 'discount', rate - say the ‘going’ interest rate available from financial markets - is used to bring all the flows to the ‘present’ so they can then be added together. An up-front capital outlay is already a 'present' valuation. The 'present value' of a cash flow one year out is obtained by dividing (or discounting) the cash flow by 1 plus the discount rate (1.06 if the discount rate was 6%). Viewed in reverse, investing the present value of that year-one cash flow in the financial market at the going interest rate would convert it into the actual cash flow one year out. The present value of a cash flow, say, four years beyond the start of the project is obtained by discounting the cash flow at the specified discount rate four times.

Say all cash flows of a project, discounted at a going 6% pa rate, added together to produce a NPV of zero (and therefore an internal rate of return equal to 6%). Risk considerations aside, the investor would be indifferent between investing in the project and, instead, putting the investment funds in the financial market. The project would be regarded as ‘marginal’ in terms of viability. A positive NPV would suggest the investment project is financially viable – and vice-versa for a negative NPV.

The net present value of a project before RRT, NPVb, when using any discount rate may be represented as:

NPVb = R - C                    (1)
where
C = sum of discounted capital expenditures in each year,
R = sum of discounted net receipts arising from the capital expenditures (gross revenue less operating costs) in each year.
To illustrate, discounting the before-tax cash flows of Figure 1 at 6% to the start of Year 1 gives a NPV of $189. The internal rate of return (the discount rate at which NPV equals zero) of those flows is 44.2%.

In the circumstances described earlier where the after-RRT outlay on capital expenditure is reduced (through immediate write-off against RRT income) by the same proportion (the tax rate) that net receipts are reduced by tax payments, the net present value after RRT, NPVt, using unchanged pre-RRT discount rate becomes:

NPVt = (R - C) (1 - t)        (2)
where
t = RRT tax rate.
Equation (2) demonstrates the investment neutrality property of an RRT under such circumstances.

In practice, sufficient positive cash flow from other RRT projects would not always be available against which to deduct immediately expenditures on a particular project - especially the early expenditures for proving and developing a stand-alone project. Where 'full loss offset' is assured through the provision (immediate or delayed) of government cash rebates for annual negative cash flow the tax design is no longer that of an RRT but of a pure cash flow tax (or Brown tax). Governments are not usually prepared to ensure full loss offset either through the provision of cash rebates (immediate or delayed) equal to annual negative cash flow times the tax rate or through allowing losses to be sold to others subject to the RRT (with government payments picking up any slack in the market for losses). The RSPT proposed by the Australian Government in May 2010, which included delayed full loss offset (incorporating loss carry-forward at the government bond rate), is an exception to this general rule.

When full loss offset is not assured by government, the carrying forward of RRT losses with interest year by year then becomes an important component of RRT design.



MISCONCEPTION 2: LOSS CARRY-FORWARD WITH INTEREST (THRESHOLD RATE) IS THE BASIS OF AN RRT

Capital expenditures (creating assets) within a project occur before the ensuing hoped for stream of positive net receipts, as illustrated in Figure 1. If no positive RRT cash flow from other projects is available against which to deduct these early capital expenditures, RRT losses (negative cash flows) will arise. RRT design has these losses carried forward with interest (at a specified RRT threshold rate) to be written off against later positive RRT cash flow.

The practical effect of this carry-forward at a threshold rate is that a project subject to the RRT will not pay tax until the project starts producing a return greater than the RRT threshold rate. This practical observation might be construed to conclude that the loss carry-forward with interest is the central design feature of an RRT. However, the main design features of a traditional RRT comprise:

Ideally, RRT losses - arising because there is insufficient positive RRT cash flow from the investor's other investment projects to absorb negative cash flows in a particular year - would be allowed to be sold to others subject to the RRT or would attract government cash rebates equal to the loss times the RRT rate. Such design would ensure 'full loss offset' is achieved by the investor in every year. This would mean that the equation (2) result - net present values of potential projects reduced by the same proportion (the tax rate) - would always be achieved. Delayed full loss offset, with losses carried forward at a risk-free rate to be later sold or subject to guaranteed government cash rebates, would also provide the same outcome.

Not surprisingly, governments do not readily provide such immediate or delayed cash rebates. The interest component on RRT losses carried forward at a threshold rate is designed to maintain the value of these deductions so that, when sufficient positive cash flow is available to the investor from activities subject to the RRT, the benefit in terms of tax savings obtained from these deductions is equivalent (in present value terms) to having full loss offset provisions. Absent government-assured full loss offset, however, the risk of not achieving the required tax savings varies greatly from project to project. At the extreme, a stand-alone project may producing no RRT receipts and attract no tax savings at all for up-front RRT losses being carried forward.

The substitution of loss carry forward at the threshold rate for the full loss offset ideal means that the neat NPV outcome of equation (2) only arises with a project in certain specific circumstances. Thus, a variety of RRT outcomes arise in the absence of full loss offset and the necessarily arbitrary specification of a single RRT threshold rate for loss carry-forward. To illustrate, in the circumstances where threshold rate equals discount rate for NPV determination:

Taking an RRT threshold rate of 6% and a discount rate of 6%, the project in Figure 1 fits into the last of these categories. Thus, with an RRT tax rate of 50%, the post-RRT NPV of the project is $94.5 - equal to the pre-RRT NPV of $189 times the 50% tax rate. The project's post-RRT internal rate of return is 29.1%, reduced below the 44.2% pre-RRT level and towards the 6% threshold rate because the early RRT losses are carried forward at 6% rather than a 44.2% rate.



MISCONCEPTION 3: LOSS CARRY-FORWARD WITH INTEREST IS ONLY RELEVANT TO AN RRT

If an RRT loss (negative cash flow) realised by a taxpayer's project in a year can be deducted, or offset, against RRT income (positive cash flow) from that taxpayer's other projects in the same year, the taxpayer achieves immediate RRT savings from the loss equal to the loss times the RRT tax rate - consistent with equation (2). The tax savings arise from the achievement of 'full loss offset' against other available RRT income. Such tax saving, however, is not confined to RRT schemes. It also occurs with income taxation. A taxpayer making a loss for income tax purposes (negative income for income tax purposes) on one activity in a particular year may have sufficient income in that same year from other activities against which to deduct the loss. Absent quarantining arrangements applying to the loss, the taxpayer achieves an immediate income tax saving from the loss equal to the loss times the taxpayer's income tax rate.

Annual RRT losses of a project arise when RRT income from the taxpayer's other projects is not available to absorb them. RRT arrangements that provide for the carrying forward of RRT losses with interest (at a specified threshold rate) are designed to provide RRT savings - made when the compounded losses are eventually written off against positive cash flow - that are the same in present value terms as the saving that would have been achieved from deduction of the loss when it originally arose. Such arrangements therefore maintain the integrity of equation (2) with its proportional reduction in pre-RRT net present values (at the RRT tax rate) forming the basis of the investment neutrality properties of an RRT. Thus, the carrying of RRT losses forward at a threshold rate is a practical surrogate for immeditae government cash rebates equal to RRT losses times the RRT tax rate, cash rebates which would achieve 'full loss offset' in all circumstances.

As with cash flow taxation, neutrality properties of income taxation systems also derive from income taxation causing a proportional reduction in pre-income-tax net present values like that of equation (2) - with a different proportional effect depending on whether the income tax system is designed to tax nominal (where again the proportion is simply the investor's income tax rate) or real income. And, like an RRT, that proportional outcome requires the achievement of full loss offset when annual losses arise. But, unlike an RRT, the proportional outcome with income taxation depends crucially on there being a wedge between pre-and post-tax discount rates. Despite that (crucial) difference in relation to discount rates, from a theoretical perspective loss carry forward with interest is required with income taxation arrangements just as much as with RRT arrangements as a surrogate for government-backed full loss offset.

Why is loss carry forward with interest not usually part of income tax laws but is seen as a crucial part of RRT arrangements? There may be three main reasons for this.

  1. Potential reductions in income tax revenue is one reason. In contests between investment neutrality and revenue, revenue is often the winner particularly when long-standing income taxation systems representing an important tax base are involved. Moreover, income tax losses - including capital losses - require particular attention from income taxation administrators to minimise scope for exploitation from taxpayers. Some income tax laws have, in fact, only relatively recently removed limits on the number of years that losses could be carried forward and allowed indefinite carry-forward of losses.

  2. Perhaps more relevant is the observation that income taxation laws do not generally encompass all the other requirements of neutral income taxation beyond full loss offset - namely, not only the inclusion of annual net receipts but also annual change in value of assets and liabilities so that the income tax base reflects taxpayers' positive and negative (ie tax losses) economic income. A movement towards the general achievement of full loss offset with income taxation - something that sectors characterised by stand-alone investments, such as the infrastructure sector, often seek - might therefore be expected to first require the income tax base to be targeting economic income. In contrast, full loss offset aside, the traditional RRT base required to achieve investment neutrality - annual cash flow excluding flows relating to borrowing and lending - is readily able to be implemented in practice.

  3. Income taxation necessarily applies across the board as its neutrality properties depend crucially, as already noted, on a wedge between pre- and post-tax discount rates, a wedge that is driven by the fact that economic income includes accrued gains and losses of investment assets and liabilities (and therefore the inclusion of interest in the income tax base). For that wedge to be reflected in investors' post-tax discount rates (what post-tax interest rate they can alternatively get from financial markets), income taxation must be applied to all activities of investors. Moreover, income taxation applying to all activities of each individual or incorporated taxpayer increases the likelihood that positive income from one activity will be available to absorb losses from another. In contrast, RRT arrangements are usually aimed at above normal profits of projects in particular sectors of an economy. These arrangements are suited to narrow sector- or project-specific application because pre-RRT discount rates are unchanged by cash flow taxation, the conceptual basis of an RRT. Moreover, with an RRT say 'ring-fencing' individual projects in a particular sector, there is no opportunity for RRT income from other projects to offset the RRT losses from any one project. RRT losses are then assured at least at the start of each individual project.

In sum, both income taxation and cash flow taxation require full loss offset to achieve investment neutrality. In contrast to income taxation in practice, however, RRT can be viewed as meeting the theoretical ideals of cash flow taxation sufficiently to justify loss carry forward with interest as a surrogate for full loss offset:



MISCONCEPTION 4: THRESHOLD RATE FOR LOSS CARRY-FORWARD SHOULD BE BASED ON LEVEL OF RISK TYPICAL OF THE INDUSTRY INVOLVED

An RRT loss from a project arises in a year when RRT expenditure on the project exceeds the project's RRT revenue in that year resulting in negative cash flow. If the developers of the project had sufficient RRT income (positive cash flow) from other projects to fully absorb the project's loss in that same year, 'full loss offset' would be achieved in that year with associated reduced RRT payments. The RRT savings associated with an RRT loss from the project in a year is then equal to the loss times the RRT tax rate.

The carrying forward of RRT losses with interest at a specified threshold rate is designed as a surrogate for 'full loss offset' when other RRT income is not available to absorb losses. Loss carry-forward with interest maintains the value of the tax savings in present value terms when the compounded loss can eventually be written off against positive cash flow. Thus, so long as a project's annual losses are eventually written off in full, the identity in equation (2) is maintained with discounting at the RRT threshold rate. The investment neutrality properties of an RRT derive from equation (2).

In this role of preserving the value of RRT losses being carried forward, what should be the basis of setting the RRT threshold rate?

Risk-free threshold rate with no unrecouped RRT losses

Say entrepreneurs were sure they would always be able to write off projects' RRT losses against future positive cash flow (that is, there would be no 'unrecouped' losses). In that case, the RRT threshold rate would logically be set at a risk-free rate of interest, such as the long-term government bond rate. The entrepreneur is sure that reimbursement for a loss will occur so the entrepreneur only has to be compensated for the opportunity cost of waiting for that sure payment to be received. The relevant risk here is not the unique risk of a project itself - or some measure of the risk typical of projects in the industry subject to the RRT - but the risk that excess deductions being compounded forward would not be offset against later positive cash flow from the project (or from other projects).

In practice, however, unrecouped losses would be common when, for example, a project turns out to be unprofitable or large closing down costs arise at the end of a project. Thus, absent a market in RRT losses, governments would have to provide arrangements that might be called 'delayed full loss offset' to ensure no project faced unrecouped losses. Such arrangements would see compounded-forward RRT losses (including losses arising on the closing down of a project) that are not able to be written off against positive cash flow attract government cash rebates equal to the compounded loss times the RRT tax rate. Delayed full loss offset provisions generally-available for all RRT losses, however, might seem to be no more likely in practice than governments' stepping in to ensure full loss offset is achieved in any year an RRT loss is realised (the government paying a cash rebate equal to the loss times the RRT tax rate in that same year in the absence of the sale of the loss to others subject to the RRT). Nevertheless, targeted arrangements providing some delayed full loss offset might be expected in practice. The Australian PRRT, for example, allows for refunds of prior RRT payments (equal to expenditure times the RRT tax rate) for eligible closing down expenditure that cannot be immediately written off against RRT receipts. Moreover, in May 2010, the Australian Government proposed the broadening of resource rent taxation in Australia by the application of a tax, called the Resource Super profits Tax (RSPT), which did incorporate delayed full loss offset and was financially equivalent to a cash flow tax. After a period of consultation, however, the government announced in July 2010 a revised proposal to broaden resource rent taxation in Australia via traditional RRT-type arrangements.

Inevitable unrecouped losses affect investment decisions

RRT losses unable to be written off against current or future positive cash flow generally do not attract commensurate government cash rebates, leaving 'unrecouped' or 'unutilised' RRT losses. The risk of unrecouped losses increases when the RRT 'ring-fences' individual projects. For example, unsuccessful exploration expenditure in a designated general mining or petroleum project area would then immediately result in unrecouped losses. More generally, unrecouped losses would be inevitable with any ring-fenced project with an internal rate of return less than the RRT threshold rate. Thus, looking across possible pre- and post-RRT internal rate of return outcomes of a particular ring-fenced project:

The effect on the spread of possible outcomes is illustrated in Figure 2. For ease of illustration, a project is chosen whose expected internal rate of return before RRT matches the RRT threshold rate. Were full loss offset achieved in every year that a loss occurs there would be no change to the pre-tax spread of outcomes because
post-RRT return then equals pre-RRT return. Unrecouped losses, however, impose an asymmetrical effect on the spread of possible outcomes. The asymmetry arises because post-RRT rates of return greater than the threshold rate, instead of following the solid pre-RRT schedule in the figure (where full loss offset provides recompense for RRT losses), would look something like the dashed schedule, reflecting pre-RRT returns reduced towards the threshold rate.

Spread of internal rate of return before and after RRT

Similarly, looking across each possible pre- and post-RRT NPV outcome of a particular project, with discounting at a risk-free interest rate (as if each outcome was certain to be achieved) and with the RRT threshold rate set equal to that risk-free interest rate:

The effect on the spread of possible NPV outcomes is illustrated in Figure 3. The project can be viewed as a marginal project before RRT with positive expected NPV balancing the spread of possible outcomes. In contrast to a symmetrical narrowing of the pre-tax spread of outcomes were full loss offset available, unrecouped losses again impose an asymmetrical effect on the spread. The asymmetry arises because negative post-RRT net present values instead of following the dashed schedule in the figure (which would be the case with full loss offset providing recompense for RRT losses) approximate the 'a'-'b' part of the pre-RRT schedule.

NPV spread before and after RRT

Load the risk-free threshold rate to offset effect of unrecouped losses

The post-RRT asymmetry imposed on both the pre-RRT internal rate of return and NPV probability distributions skews these distributions negatively, reducing expected internal rate of return and NPV. The somewhat predictable nature of these effects under an RRT might suggest that RRT parameters could be adjusted to minimise the effect of an RRT on investment decision-making. Starting from the benchmark of a risk-free RRT threshold rate when there is no risk of unrecouped losses, the threshold rate might be increased above the risk-free rate (perhaps accompanied by a reduced RRT tax rate) in a rough attempt at minimising the distortive effect imposed by the possibility of unrecouped losses. Increasing the threshold rate would:

Thus, expected internal rate of return would be increased in Figure 2 and expected NPV increased in Figure 3.

Increasing the RRT threshold rate above a risk-free rate, perhaps in conjunction with a somewhat reduced RRT tax rate, might therefore be viewed as a rough offset to the asymmetrical effects illustrated in Figures 2 and 3 caused by the carrying forward of RRT losses with interest as a substitute for (immediate or delayed) full loss offset provisions. The further the RRT design increases the possibility of full loss offset - for example, company-based rather than project-based or losses arising from closing down expenditure attracting cash rebates - the lower such a loading of the RRT threshold rate would be above a risk-free rate.

Regardless of the use of loadings above a risk-free rate, however, distortions associated with the asymmetric effect of the RRT on a project's spread of possible outcomes will inevitably remain. A loading does not directly compensate outcomes where unrecouped RRT losses arise. Moreover, a generally-applicable loading is not sensitive to the risk of unrecouped losses faced by particular projects. A project may, for example, have a wide spread of possible outcomes but have little or no prospect of losing available RRT deductions - in which case, no loading is justified. Against such considerations, an alternative strategy is to design the RRT to maximise the possibility of full loss offset and leave the threshold rate at a risk-free level - a level at which income taxpayers would, no doubt, be more than pleased to accept on their losses being carried forward, despite the risk that compounded-forward income tax losses could ultimately be lost completely.

Additive or multiplicative loadings on risk-free threshold rate

The form of the loading of the threshold rate above a risk-free rate could be either additive or multiplicative. The above rationale for a loading does not preclude a multiplicative loading. Against the above analysis, the loading would be designed to offset the effects of the skewing of the range of possible project outcomes by unrecouped losses.

The two forms of loading result in very different threshold rates with changes in long-term bond rates. With the Australian PRRT, the loading is additive: initially set in 1984 at 15 percentage points above the long-term government bond rate, when the bond rate was about 14 to 15 per cent. In 1984, a multiplicative loading providing an equivalent percentage threshold rate would have been 2 times long-term bond rate. In early 2010, however, with the long term bond rate at about 5%, the 15% additive formula provides a threshold rate of 20% whereas a 2-times multiplicative rate would provide a threshold of 10%.



MISCONCEPTION 5: THE THRESHOLD (OR UPLIFT) RATE DEFINES WHAT ECONOMIC RENT (OR EXCESS PROFITS) AN RRT TAXES

An RRT may be applied on a project basis where costs associated with a defined project can only be offset against revenue from that same project. In these circumstances, up-front exploration and development expenditures create losses because of the inevitable delay in foreshadowed future revenue. These losses are carried forward at the threshold (or uplift) rate. Thus, the project does not start paying RRT until a return is achieved on those early costs equal to the uplift rate. Not surprisingly, therefore, people conclude that the uplift rate is a key design parameter required to determine the level of profit above which an RRT 'kicks in'. This conclusion, however, ignores the characteristics of cash flow taxation that underpin the neutrality properties of an RRT. A pure cash flow tax (or Brown tax) has no uplift rate at all as losses attract immediate cash rebates. And yet inherent in the design of a Brown tax is the taxing of above normal returns from whatever source (generally termed 'economic rent').

Brown tax

To illustrate the economic rent taxing characteristic of a Brown tax, take an investor with a 15% risk-weighted discount rate (that is, someone requiring a 15% pa return from the expected cash flows of a proposed mining investment). Say, in the event, that investor does actually earn 15% pa before tax from the highly stylised mining investment in Table 3 ('Pre-tax cash flow' column) - with that return to $1000m of development expenditure at the start of Year 1 (Year 0) coming from delayed net receipts (revenue less operating costs) in Years 3, 4 and 5. With the mining project subject to a 40% Brown tax, that investor looking back at the past stream of government cash rebates in Year 0 and tax payments in Years 3, 4 and 5 ('Brown tax rebates/tax' column) finds that he has paid no tax in discounted terms. Tax payments associated with the investment (in its later years) when discounted at the investor's 15% discount rate just balance the up-front $400m cash rebate to provide a zero NPV. But had the investment earned more than 15% - earning economic rent from the investor's point of view - the investor would then see the government taking out more than it put in. If, instead of 15%, the investor uses a 6% discount rate, the investor would view the project’s tax payments as exceeding the early cash rebate by $137m in discounted terms. The economic rent above the investor’s 6% required return would be seen by the investor as being subject to tax. Economic rent is in the eye of the investor and the inherent design of the Brown tax allows that personal view of economic rent to play out.

TABLE 3: Cash flows of stylised mining project subject to a 40% Brown tax (a)
YearCapital
expenditure
$m
Net receipts
$m
Pre-tax cash
flow
$m
Brown tax
rebates/tax
$m
Post-Brown tax
cash flow (b)
$m
010000-1000-400(c)-600
100000
200000
30780780312468
40662662265397
50219669268401
NPV @ 15%--ZeroZeroZero(d)
NPV @ 6%--342.6137.0205.6(d)
IRR--15%15%15%(e)

Notes to table:

  1. Immediate expensing of all costs and immediate cash rebates for tax losses, so that negative cash flow is reduced by 40% rebate and positive cash flow is reduced by 40% tax.
  2. Pre-tax cash flow less (negative) Brown tax rebates and (positive) tax payments.
  3. Cash rebate equal to 40% of $1000 capital expenditure.
  4. 60% of pre-tax NPV - ie pre-tax NPV reduced by the 40% Brown tax rate as shown in equation (2).
  5. With all positive and negative cash flow reduced by the 40% tax rate, the internal rate of return is the same after tax as before.

If 6% were a risk-free interest rate, the cash flows in Table 3 and the associated NPV with discounting at 6%, could be one possible outcome of a proposed investment. In terms of Figure 3, this possible outcome with a positive pre-tax NPV would fall to the right of the y-axis (which cuts the x-axis at zero NPV), with the NPV reduced by 40% after the Brown tax to $205.6m. An outcome where the $1000m up-front capital expenditures were totally unsuccessful, the pre-tax NPV would be well to the left of the y-axis - but again would be cut by 40% after the government cash rebate under the Brown tax. The Brown tax acts even-handedly on both ends of the project's risk spectrum.

The rent-taxing and associated neutrality properties of a Brown tax remain at the heart of an RRT. In moving from a Brown tax with full loss offset to an RRT, losses are carried forward at an uplift rate with the attendant risk that insufficient RRT revenue will mean the value of the losses will never be recouped. Nevertheless, the irrelevance of the RRT uplift rate to define what is economic rent remains. Under an RRT, the uplift rate is designed to maintain the value of the losses carried forward in order to achieve an outcome equivalent to full loss offset when the losses are deducted against future revenue. The uplift rate is not designed to define economic rent or excess profits. Thus, if government undertakes to provide cash rebates for losses compounded forward so that there is no risk that the value of these losses will be lost, the uplift rate need just reflect a risk-free rate (say the government bond rate) to maintain the value of the losses. Such design could be described as a Brown tax with delayed full loss offset. Uplift at the government bond rate maintains the value of losses over time (until they are either absorbed by positive cash flow or attract government cash rebates). The uplift rate has nothing to do with determining when the tax 'kicks in' and nothing to do with the cost of funds to the investor.

Brown tax with delayed full loss offset

Table 4 uses the project in Table 3 to illustrate how the uplift rate should be set a risk-free rate (just to maintain the value of losses) when a cash flow tax with delayed full loss offset applies to the project. Thus, pre-tax return is again 15% and pre-tax NPV zero for the investor using a 15% risk-weighted discount rate. In contrast to the Table 3 outcome under full loss offset, aggregate post-tax outcomes in Table 4 (with losses carried forward at a 6% risk-free rate) are an 11.8% return and an NPV of -$95.2m with discounting at 15% (column (d)). Taken on face value, these post-tax results showing the 15% pre-tax return reduced to 11.8% and a negative NPV for the investor with a 15% discount rate suggest the project, marginal before tax, has been made sub-marginal by the imposition of tax.

The final column in Table 4 shows the problem with this interpretation of post-tax cash flows. The final column - column (f) - is the difference between aggregate post-tax cash flow (column (d)) and cash flow if a pure Brown tax were operative (column (e)). The up-front difference of -$400m reflects the lack of an immediate government cash rebate for the $1000m of capital expenditure. That deficiency relative to pure cash flow taxation is fully recovered by the lower tax payments (again relative to cash flow taxation) of $312m in Year 3 and $174m in Year 4 arising because the loss associated with the $1000m up-front outlay is compounded forward at 6% and offset against project net receipts in those years. Because government undertakes to provide cash rebates in the event insufficient net receipts are available to fully absorb compounded-forward losses, the cash flows in the final column can be viewed as a risk-free asset of the investor. Consequently, it would be misleading financially for the investor to discount the cash flows of this risk-free asset at his 15% risk-weighted discount rate. And, as shown in Table 4, the aggregate post-tax NPV of -$95.2m (in column (d)) arises solely because the risk-free component of the aggregate post-tax flows is discounted at 15% - producing the -$95.2m in column (f) - rather than at the 6% risk-free rate.

TABLE 4: Cash flows of stylised mining project subject to 40% cash flow tax (immediate expensing
of capital expenditure) with delayed full loss offset and 6% uplift (a)
YearCapital
costs

$m
Net
receipts

$m
Pre-tax
cash flow

$m
Base after
loss uplift
(b)
$m
Tax
payments
(c)
$m
Post-tax
cash flow
(d)
$m
Post-Brown
tax cash flow
(e)
$m
Cash flows (d)
less (e)
(f)
$m
010000-1000-10000-1000-600-400
1000-10600000
2000-11240000
30780780-4110780468312
4066266222690571397174
5021921921988131131 0
NPV@15%--Zero---95.2(g)Zero(h)-95.2
NPV@6%--342.6--205.6(i)205.6(h)Zero
IRR--15%--11.8%(j)15.0%(k)6.0%(l)

Notes to table:

  1. Immediate expensing of all costs and tax losses (negative cash flow) compounded forward at risk-free 6% and, if insufficient revenue available, compounded-forward losses remaining at end of project attract a 40% government cash rebate.
  2. Prior year negative cash flow uplifted by 6% plus pre-tax cash flow this year.
  3. 40% times any positive tax base after loss uplift.
  4. Pre-tax cash flow less tax payments.
  5. Pre-tax cash flow times 60% or the cash flow (see Table 3) that would result if a 40% Brown tax reduced all positive and negative cash flows by 40%. Because of government cash rebates for losses not absorbed by project revenue, the value of a loss in any year is the loss times the 40% tax rate. These cash flows reflect the risky component of the project's cash flows.
  6. Post-tax cash flow less tax flow if a Brown tax were applying - ie (d)-(e). The negative amount in Year 0 is shortfall in cash flow under the tax relative to a Brown tax (arising because losses are compounded forward rather than attracting an immediate cash rebate). This shortfall is made up in Years 3 and 4 through higher cash flow arising from the Year 0 loss, uplifted at the risk-free 6%, being deducted against positive cash flow in those years. Because government cash rebates would cover these compounded forward losses in the absence of sufficient revenue, these cash flows reflect the risk-free component of the project's cash flows.
  7. Aggregate post-tax cash flow has a negative NPV with discounting at 15%. However, separating the aggregate post-tax cash flows into risky (e) and risk-free (f) components, results in the NPV of the risky component being equal to 60% of pre-tax NPV (regardless of the discount rate applied to both pre- and post-tax cash flow). With this separation, the negative NPV of aggregate flows is seen to arise solely from discounting the risk-free component at 15% instead of the 6% risk-free rate.
  8. 60% of pre-tax NPV - ie pre-tax NPV reduced by the 40% Brown tax rate
  9. With discounting at the 6% risk-free rate, aggregate post tax cash flow has a NPV that is 60% of pre-tax NPV. That is because the risk-free component of project cash flows has a zero NPV at this discount rate (the discount rate matches the loss uplift rate). This outcome fits well with the building up of NPV probability distributions using a risk-free rate (Figure 3).
  10. The internal rate of return of the aggregate post-tax cash flow is reduced below the pre-tax return. As with NPV, however, separating the aggregate post-tax cash flows into risky (e) and risk-free (f) components, results in the IRR of the risky component being equal to the pre-tax IRR.
  11. With all positive and negative cash flow reduced by the 40% tax rate, the internal rate of return is the same after tax as before.
  12. The IRR of the risk-free component of the project's post-tax cash flows matches the 6% (risk-free) loss uplift rate.

Excising the risk-free component (column (f)) from aggregate post-tax cash flows leaves what can be viewed as the risky project cash flows in column (e). Those risky cash flows are post-Brown tax cash flows. Thus, not surprisingly, when those flows are discounted at 15%, a NPV of zero results. With correct financial analysis, the project remains marginal after tax. With discounting at 6% the project would again have a positive $342.6m pre-tax NPV (as one possible outcome in the spread of outcomes illustrated in Figure 3) with post-tax NPV reduced by 40% to $205.6m.

Taxes financially equivalent to a Brown tax

A financially equivalent outcome to that in Figure 4 could be achieved (as shown in Figure 5) by: (1) changing immediate write-off of capital expenditure to write-off over a number of years; and (2) providing extra deductions each year equal to last year's written-down value of capital assets times the uplift rate. A tax with this design - called the Resource Super Profits Tax (RSPT) - was proposed, but later replaced by proposed RRT arrangements, by the Australian Government in May 2010 to apply to Austarlian mining and petroleum projects (with write-off details to be subject to consultation processes). The design incorporated government guaranteed cash rebates for losses compounded forward at an uplift rate equal to the long-term government bond rate (LTBR). As with a cash flow tax incorporating delayed full loss offset (Table 4), the uplift rate is set at a risk-free rate to maintain the value of losses until the ensured utilisation of those losses occurs. Again, the uplift rate has nothing to do with determining when the tax 'kicks in' and nothing to do with the cost of funds to the investor.

Losses created from annual write-off allowances plus uplift rate applied to written-down value and compounded forward at the uplift rate must be equivalent to losses created from immediate expensing and compounded forward at the same uplift rate. This is illustrated in Figure 5 which varies from Figure 4 only by 5-year straight line write-off applying to the $1000m of up-front capital expenditure instead of immediate expensing. It turns out that the post-tax cash flows in Figure 5 are exactly the same as in Figure 4, with $90m tax paid in year 4 and $88m tax paid in Year 5 in both cases. That occurs with this particular project because with capital write-off over 5 years or less (including the immediate expensing in Table 4), compounded-forward losses are the same to Year 4 when all the losses are absorbed.

TABLE 5: Cash flows of stylised mining project subject to 40% cash flow tax (5-year write-off
of capital expenditure) with delayed full loss offset and 6% uplift (a)
YearPre-tax
cash flow
(b)
$m
Capital
write-off
(c)
$m
Depreciated
value
(d)
$m
Tax value
uplift
(e)
$m
Base before
loss uplift
(f)
$m
Base after
loss uplift
(g)
$m
Tax
payments
(h)
$m
Post-tax
cash flow
(i)
$m
Post-Brown
tax cash flow
(j)
$m
Cash flows (i)
less (j)
(k)
$m
0-10002008000-200-2000-1000-600-400
1020060048-248-4600000
2020040036-236-7240000
378020020024556-2110780468312
466220001245022690571397174
521900021921988131131 0
NPV@15%Zero-------95.2Zero-95.2
NPV@6%342.6------205.6205.6Zero
IRR15%------11.8%15.0%6.0%

Notes to table:

  1. Five-year straight line write-off of non-exploration capital costs with extra deductions equal to 6% (risk-free uplift rate) of depreciated value, tax losses compounded forward at 6% uplift rate and, if insufficient revenue available, compounded-forward losses remaining at end of project attracting a 40% government cash rebate. Because the project's tax payments are the same under this design as in Table 4, NPV and IRR results are also the same as in Table 4.
  2. As in Tables 3 and 4.
  3. Five-year straight line write-off of $1000 capital expenditure in Year 0.
  4. Capital expenditure less all depreciation allowed to date.
  5. Prior year depreciated value times 6%.
  6. Net receipts (Tables 3 and 4) less depreciation less tax value uplift.
  7. Prior year negative amount uplifted by 6% plus column (f) amount ('tax base before loss uplift') this year.
  8. 40% times any positive amount in column (g), or the 'tax base after loss uplift'. The year-by-year tax payments are the same as in Table 4 (where immediate expensing of capital expenditure applies). That is because with 5-year write-off tax losses from annual write-off allowances plus uplift applied to written-down value provide exactly the same compounded forward losses to Year 4 (where the losses are fully absorbed) as does immediate expensing. With this project, capital write-off over 5 years or less produces the same tax payment stream. For write-off over periods longer than 5 years (Table 6), the present value of the stream of tax payments matches that in Tables 4 and 5 with discounting at 6%.
  9. Pre-tax cash flow less tax payments (same as in Table 4).
  10. Pre-tax cash flow times 60% (as in Tables 3 and 4).
  11. Post-tax cash flow less tax flow if a Brown tax were applying - ie (i)-(j) - as in Table 4.

Table 6 shows a stream of tax payments plus final year government cash rebate different to that in Table 5 as a result of 10-year straight line write-off applying rather than 5-year write-off. The government cash rebate in Year 5 applies to the loss in that year created by the deduction of the $500m of written-down value of assets at that time. As a result of the 10-year write-off, the 'payback' of the $400m deficiency in aggregate post-tax cash flow in Year 0 relative to that of a Brown tax takes longer - as shown by the amounts in Years 3, 4 and 5 in the project's risk-free asset (last column of Table 6) relative to those in column (k) of Table 5. Nevertheless, the risk-free asset still has an NPV of zero with discounting at the 6% LTBR and the risky component of the aggregate post-tax flows (penultimate column) matches those of a Brown tax applied to the project. Regardless of the period of write-off, this tax design is financially equivalent to cash flow taxation. And, to reiterate, the uplift rate has nothing to do with determining when the tax 'kicks in'. It maintains the year-by-year value of losses being carried forward and ensures the financial equivalence of the tax design to a Brown tax.

TABLE 6: Cash flows of stylised mining project subject to 40% cash flow tax (10-year write-off
of capital expenditure) with delayed full loss offset and 6% uplift (a)
YearPre-tax
cash flow
$m
Capital
write-off
$m
Depreciated
value
$m
Tax value
uplift
$m
Base before
loss uplift
$m
Base after
loss uplift
$m
Tax
payments
$m
Post-tax
cash flow
$m
Post-Brown
tax cash flow
$m
Cash flow diff
with Brown tax
$m
0-10001009000-100-1000-1000-600-400
1010080054-154-2600000
2010070048-148-4240000
378010060042638-18976704468236
46621005003652652621045139754
5219500(b)030-311-311-124(c)343131 212
NPV@15%Zero-------108.0Zero(d)-108.0
NPV@6%342.6------205.6(e)205.6Zero
IRR15%------11.5%15.0%6.0%

Notes to table:

  1. The only difference in tax design in this table and that in Table 5 is 10-year straight line write-off of non-exploration capital rather than the 5-year write-off in Table 5.
  2. At end of project, the $500m written-down value of capital assets is a deduction. The assets are assumed to be scrapped then for zero value.
  3. The $311m loss in the final year attracts a cash rebate of $124m equal to the loss times the 40% tax rate.
  4. Despite the increased negativity (compared to Table 5) of the NPV of aggregate post-tax cash flow with 10-year write-off with discounting at 15%, when the risky and risk-free components are separated, the NPV of the risky component stays at zero - the same as the project's pre-tax NPV - with discounting at 15%. Again, the -$108m NPV of aggregate post-tax flows arises solely from discounting the risk-free component of those flows at 15% instead of the 6% risk-free rate.
  5. Because the cash rebate in Year 5 and the tax payments in prior years discount to the same present value as the tax payments in Tables 4 and 5, with discounting at the risk-free 6% rate, the NPV of post-tax flows is also the same as that in Tables 4 and 5 (again with discounting at 6%).

As in the case of the Brown tax in Table 3, under the tax arrangements incorporating delayed full loss applied in Tables 4, 5 and 6, when the $1000m of up-front capital expenditure is totally unsuccessful, the pre-tax NPV (-$1000m) would be cut by 40% after guaranteed government cash rebates (appropriately discounted at a risk-free rate). That is very different from the outcome in these circumstances under an RRT (that is, where full loss offset, delayed or immediate, does not apply).

RRT

With an RRT, the uplift (or threshold) rate applied to losses being carried forward is seeking to achieve equivalence with the full loss offset ideal of a Brown tax (as does the risk-free uplift rate in the delayed full loss offset arrangements associated with the tax design applied in Tables 4, 5 and 6). Thus, the RRT uplift rate is aimed at maintaining the value of RRT losses being carried forward pending offset against future RRT profits. A loading in the uplift rate above the government bond rate might be viewed as either:

However, no amount of juggling various forms and levels of loading above a risk-free rate can remove an RRT's asymmetrical impact across a project's risk spectrum.

Once full loss offset is dropped, along with its neutrality benefits, there are no neat second-best solutions.

Nevertheless, if an RRT with a 15% uplift rate applied to the cash flows of the project in the above tables, zero RRT would be paid, consistent with the outcome under a Brown tax for the investor with a 15% risk-weighted discount rate (Table 3). The project has a pre-tax return of 15% and the $1000m loss from the up-front capital expenditure, when compounded forward at 15% pa under the RRT, just absorbs the last dollar of net receipts of the project in the last year of the project. This is shown in Table 7.

TABLE 7: Cash flows of stylised mining project subject to 40% RRT with 15% uplift rate (a)
YearCapital
costs

$m
Net
receipts

$m
Pre-tax
cash flow

$m
Base before
loss uplift

$m
Base after
loss uplift
(b)
$m
Tax
payments
(c)
$m
Post-tax cash
flow
(d)
$m
010000-1000-1000-10000-1000
10000-115000
20000-132300
30780780780-7410780
40662662662-1900662
5021921921900219
NPV@15%--Zero---Zero
NPV@6%--342.6---342.6
IRR--15%---15.0%

Notes to table:

  1. Immediate expensing of all costs and tax losses (negative cash flow) compounded forward at 15% (lost completely if insufficient revenue available).
  2. Prior year negative amount uplifted by 15% plus this year's amount in 'Base before loss uplift' (or pre-tax cash flow).
  3. 40% times any positive tax base after loss uplift.
  4. Pre-tax cash flow less tax payments.

With discounting at the investor's assumed 15% discount rate, the project has a zero NPV before and after the RRT. The investor using a 15% risk-weighted discount rate perceives zero tax payable in discounted terms under the Brown tax (Table 3) and literally zero tax payable under the RRT (Table 7). This outcome might be interpreted to mean that the RRT uplift rate, necessarily higher than a risk-free rate, represents an arbitrary guess at a measure of economic rent for all investors and all projects subject to the RRT. That interpretation, however, leads to the incorrect conclusion that a risk-free uplift rate used with a cash flow tax incorporating delayed full loss offset (Tables 4, 5 and 6) is also a measure of when the tax 'kicks in'. This important interpretive issue aside, a fixed RRT uplift rate can only be appropriate for specific investors and particular projects.

Thus, while the investor's 15% risk-weighted discount rate applied to the single possible project outcome under an RRT with a 15% threshold rate in Table 7 appears to provide neat, but isolated, equivalence to cash flow taxation in Table 3, the distortive asymmetric effects of an RRT across the full range of possible project outcomes remain.

Moreover, with some mining projects, after successful exploration expenditure, there may be little or no risk that losses associated with subsequent development and operating expenditures would be lost completely - despite the project exhibiting a wide spread of different possible outcomes. In these circumstances, an uplift rate in line with a risk-free rate would provide the desired equivalence to full loss offset. An uplift rate set at some average measure of investors' risk-weighted discount rates would raise the prospect of perverse investment and production decisions.

Conclusion

In circumstances where government does not wish to provide cash rebates for losses under cash flow taxation, a practical conclusion to the above discussion is to design an RRT which approaches a Brown tax as much as practicable. Such design might include the following features:

The tax would be implemented against the understanding that the downside of security of tax revenue is that some RRT losses may not be utilised. Despite that, the risk-free uplift rate reflects the closeness of design to a Brown tax which implicitly deals with each investor's perception of the economic rent associated with particular investments. Such an uplift rate aims at maintaining the value of any losses carried forward and is not a measure of where the tax 'kicks in'.

Under such an approach to RRT design any uplift rate significantly above a risk-free level would necessarily imply attendant risk of losing the value of RRT losses through such design features as 'ring-fenced' exploration expenditure, no sale of losses allowed and no refunds for specified closing down expenditure - but would also carry with it the prospect of investment and production decisions driven by tax design rather than genuine commercial motive.



MISCONCEPTION 6: THE INTERRELATIONSHIP BETWEEN RRT (OR CASH FLOW TAXES GENERALLY) AND INCOME TAXATION RAISES NO SPECIAL ISSUES

A pure cash flow tax, or Brown tax, will exhibit its investment neutrality properties regardless of the cash flows to which it is applied. Thus, if applied to post-income tax flows, post-income tax internal rates of return (IRRs) will be maintained after the Brown tax and post-income tax net present values (NPVs) will be reduced in proportion to the Brown tax rate, regardless of the (post-income tax) discount rate used.

A practical difficulty associated with applying a Brown tax to say the mining industry after income tax is the requirement to attribute the right amount of a taxpayer’s overall income tax liability to the taxpayer’s mining operations to get a true measure of post-income tax flows of the mining operations.

With a Brown tax applied before income tax, an interesting question is whether the neutrality properties of cash flow taxation are maintained after the application of income taxation. Typically, cash rebates and/or tax payments from cash flow taxation are assigned simple income tax treatment incorporating:

  1. cash rebates for negative pre-tax cash flow included in assessable income; and

  2. tax payments on positive pre-tax cash flow allowed as an income tax deduction.

The question of interest is whether such simple income tax design allows the neutrality properties of a Brown tax to flow through subsequent income taxation or whether alternative income tax design is required.

This issue is assessed here using a stylised mining project over 5 years with typical delay between up-front capital investment and realisation of revenue from product sales. Three different cases are analysed, each with a different income tax treatment:

  1. 5-year straight line write-off of capital expenditure with cash rebates for negative pre-tax cash flow assessable and Brown tax payments deductible;

  2. economic depreciation – annual change in pre-tax value of the project (increases, as well as decreases) – included in the income tax base, again with cash rebates for negative pre-tax cash flow assessable and Brown tax payments deductible; and

  3. economic depreciation applying but this time with the annual change in value of the project that is included in the income tax base determined from cash flows of the project after the application of the Brown tax (rather than the project’s pre-tax cash flows).

In each case, full loss offset is assumed both with cash flow taxation and income taxation.

The project

The highly stylised mining project under study has the following pre-tax cash flows:

The project before any taxation is shown in Table 8 and illustrated in Figure 4.

TABLE 8: Project cash flows before tax
YearCapital expenditure
$m
Net receipts
$m
Pre-tax cash flow
$m
Project value (a)
$m
010000-10001000
10001100
20001210
30562562769
40477477369
504064060
NPV @ 10%--Zero-
IRR--10%-

Notes to table:

  1. Future cash flow discounted at 10%.

Project value before taxes
FIGURE 4: Project value before taxes


Before all taxes, the project has an IRR of 10% and, with discounting at 10%, a NPV of zero. For the purposes of this stylised project, the investor could alternatively earn 10% by investing in the financial market. Thus, the project would be marginal for an investor using a pre-tax 10% discount rate to assess project viability. Project value increases in Years 1 and 2 as the project becomes closer to yielding tangible net receipts and then declines as the mineral resource is used up with no value remaining at end Year 5.

Analysis

Case 1. Table 9 has a 40% Brown tax applying to the project's cash flows (revenue from the sale of product less capital and operating costs). Thus, negative cash flow attracts a cash rebate equal to the loss times 40% and positive cash flow attracts tax at 40%. The tax outcomes for the project under the Brown tax with full loss offset achieved via cash rebates would be the same as those under an RRT where annual losses (incorporating immediate write-off of capital expenditure) could be offset against RRT profits from the taxpayer's other projects. Table 9 shows in column (c) that the IRR of the project post-Brown tax stays at the pre-tax 10% and its NPV (with the discount rate unchanged at the 10% pre-tax rate) stays at zero. These outcomes result from all the project’s pre-tax cash flows (negative as well as positive) being reduced by the 40% tax rate. The project remains marginal after the Brown tax.

TABLE 9: 5-year straight line depreciation, Brown tax cash rebates assessable, Brown tax payments deductible
YearPre-tax cash
flow
(a)
$m
Brown rebates
/tax payments
(b)
$m
Post-Brown
tax cash flow
(c)
$m
Income tax
depreciation
(d)
$m
Income tax base
pre-Brown tax
(e)
$m
Income tax base
post-Brown tax
(f)
$m
Income tax
payments
(g)
$m
Post-all taxes
cash flow
(h)
$m
0-1000-400-60000400120-720
1000200-200-200-6060
2000200-200-200-6060
356222533720036213741296
44771912862002778626260
54061622432002064313230
NPV@10%Zero-Zero-----7.1
IRR10%-10%----6.7%

Notes to table:

  1. From table 8.
  2. Pre-tax cash flow (column (a)) times 40% tax rate. Negative number represents a cash rebate and positive numbers tax payments
  3. Column (a) less column (b).
  4. 5-year straight line depreciation of capital expenditure for income tax purposes.
  5. Net receipts (Table 8) less depreciation allowances (column (d)).
  6. Column (e) less Brown tax rebates/payments (Column (b)) making the rebates assessable and Brown tax payments deductible.
  7. Column (f) times 30% income tax rate. Income tax losses are able to be written off immediately against the taxpayer's other income.
  8. Column (a) less column (b) less column (g).

In fact, the investor sees that he has paid no Brown tax in discounted terms. The Brown tax payments made in Years 3 to 5 (column (b) in Table 9), when discounted at 10%, match the $400m up-front amount in Year 0 ($400m government cash rebate under the Brown tax or, under an RRT, the effect of offsetting the write-off of the $1000 capital outlay in Year 0 against positive RRT cash flow of other projects).

Table 9 also shows outcomes after the Brown tax and after income tax applied at 30% with 5-year straight line write-off allowed - column (e) includes net receipts less depreciation and column (f) includes Brown tax rebates and payments. The project’s IRR falls to 6.7% after Brown and income taxes (column (h)). Its NPV is -$7.1, this time with discounting at 7% – that is, 10x(1-0.3)% to take into account the wedge imposed by income taxation between pre- and post-tax discount rates. Before income tax the investor compares project returns with the 10% available from the financial market. After income tax at the investor's 30% income tax rate, the investor compares project returns with the post-tax 7% financial market return.

On the basis of these static figures, the project has moved from being marginal before tax and after Brown tax to being slightly below the margin after both Brown and income taxes (that is, a return of 6.7% instead of 7% and a NPV of -7.1m rather than zero). Either the 5-year straight line depreciation (illustrated in Figure 5) or the treatment of the Brown tax for income tax purposes, or both, might be causing this.

Project value and tax value with 5-year straight line depreciation
FIGURE 5: Project value and tax value with 5-year straight line depreciation


Case 2 changes the income tax depreciation arrangements and Case 3 the Brown tax treatment for income tax purposes.

Case 2. Table 10 has economic depreciation replacing 5-year straight line income tax depreciation - in the ‘Income tax depreciation' column (d). This means annual change in value of the project shown in the last column of Table 8 and illustrated in Figure 4 (or project cash flow discounted at 10% to end of year less cash flow discounted to start of year) is included in the income tax base. Thus, accrued capital gains of $100m and $110m are included for Years 1 and 2, respectively, with accrued capital losses allowed in ensuing years as the mineral resource is used up. To that are added annual net receipts (from Table 8) to compute column (e) and then Brown tax cash rebates – or the effect of negative cash flow being applied against other positive cash flow with an RRT – less Brown or RRT tax payments to compute column (f).

TABLE 10: Economic depreciation, Brown tax cash rebates assessable, Brown tax payments deductible
YearPre-tax cash
flow
(a)
$m
Brown rebates
/tax payments
(b)
$m
Post-Brown
tax cash flow
(c)
$m
Income tax
depreciation
(d)
$m
Income tax base
pre-Brown tax
(e)
$m
Income tax base
post-Brown tax
(f)
$m
Income tax
payments
(g)
$m
Post-all taxes
cash flow
(h)
$m
0-1000-400-60000400120-720
1000-10010010030-30
2000-11011011033-33
3562225337441121-104-31368
447719128640077-114-34321
540616224336937-125-38281
NPV@10%Zero-Zero-----31.4
IRR10%-10%----5.8%

Notes to table:

  1. From table 8.
  2. Pre-tax cash flow (column (a)) times 40% tax rate. Negative number represents a cash rebate and positive numbers tax payments.
  3. Column (a) less column (b).
  4. Economic depreciation (annual change in value) of project from Table 8 included for income tax purposes. Negative values represent assessable accrued capital gains, positive values deductible accrued capital losses.
  5. Net receipts (Table 8 or Years 3 to 5 in column (a)) less economic depreciation (column (d)).
  6. Column (e) less Brown tax rebates/payments (Column (b)) making the rebates assessable and Brown tax payments deductible.
  7. Column (f) times 30% income tax rate. Income tax losses are able to be written off immediately against the taxpayer's other income.
  8. Column (a) less column (b) less column (g).

In the absence of Brown taxation, income tax applying to net receipts plus economic depreciation would see the project’s IRR coming in at 7% – corresponding to the project’s 10% pre-tax return reduced by the 30% income tax rate. With discounting at 7%, the project’s NPV would be zero. The project, marginal before tax, would remain marginal after income tax.

However, with Brown tax cash rebates and payments being assessable and deductible, respectively, Table 11 shows the project has an IRR of 5.8% and an NPV of -$31.4m after Brown tax and income tax. On these numbers, the treatment in the table of Brown taxation for income tax purposes has a somewhat adverse effect on the project’s viability. Against that, substituting economic depreciation (and its taxation of the project's early accrued capital gains) with relatively generous 5-year straight line depreciation - the tax treatment in Table 9 - pushes the project's after-all taxes outcome closer to that of a marginal investment.

In sum, relative to a neutral post-tax outcome, the generosity of 5-year write-off compared to economic depreciation for this project is offset by the treatment of Brown taxation for income tax purposes - resulting in the 'slightly below the margin' outcome of Table 9.

Case 3 keeps economic depreciation for income tax purposes and changes the income tax treatment of the Brown tax.

Case 3. Table 11 has economic depreciation again applying but this time annual change in project value is not determined from pre-tax cash flow. It is determined from pre-tax cash flows after the impact on those flows of the Brown tax (Figure 6). The effect of the Brown tax is to reduce all pre-tax flows (capital expenditures, net receipts and any residual value of the project) by the 40% Brown tax rate.

TABLE 11: Economic depreciation based on post-Brown tax cash flow
YearPre-tax cash
flow
(a)
$m
Brown rebates
/tax payments
(b)
$m
Post-Brown
tax cash flow
(c)
$m
Income tax
depreciation
(d)
$m
Income tax base
post-Brown tax
(e)
$m
Income tax
payments
(f)
$m
Post-all taxes
cash flow
(g)
$m
0-1000-400-600000-600
1000-606018-18
2000-666620-20
35622253372647322315
44771912862404314273
5406162243221227237
NPV@10%Zero-Zero---Zero
IRR10%-10%---7.0%

Notes to table:

  1. From Table 8.
  2. Pre-tax cash flow (column (a)) times 40% tax rate. Negative number represents a cash rebate and positive numbers tax payments
  3. Column (a) less column (b).
  4. Economic depreciation (annual change in value) of post-Brown tax cash flow (column (c) cash flow discounted at 10% to end of year less cash flow discounted to start of year) included for income tax purposes. Negative values in column (d) represent assessable accrued capital gains, positive values deductible accrued capital losses.
  5. Post-Brown tax net receipts (Years 3, 4 and 5 of column (c)) less economic depreciation post-Brown tax cash flow (column (d)).
  6. Column (e) times 30% income tax rate.
  7. Column (a) less column (b) less column (f).

Project value pre-tax and post-Brown tax
FIGURE 6: Project value pre-tax and post-Brown tax


The resulting annual change in value of the post-Brown tax project flows (again in the ‘Income tax depreciation’ column) in each year in Table 11 is 40% less than the corresponding change in value in Table 10.

The income tax base in each year (the ‘Income tax base post-Brown tax’ column) in Table 11 then comprises the post-Brown tax net receipts (in Years 3, 4 and 5 of column (c)) less economic depreciation based on post-Brown tax cash flows (column (d)). Brown tax payments and cash rebates are not separately included as they have already been excluded from the pre-tax project flows.

The outcome of this treatment is a post-tax project IRR of 7% and an NPV of zero with discounting at the income tax-affected 7% discount rate. The project, marginal before tax, is again marginal after Brown tax (or RRT with full loss offset) and income tax.

Conclusion

From a theoretical perspective, the interaction of a Brown tax applied to mining projects before income tax and income taxation is a relevant issue in relation to neutrality of investment decisions. Change in project value – a key component of a neutral income tax base – needs to be determined on the basis of the project’s post-Brown tax cash flows, not its pre-tax cash flows, to meet the neutral ideal.

Nevertheless, there is probably no point contemplating such treatment in practice unless:

Income arrangements often do not closely track annual change in value of mining projects. Some mining expenditures might be capitalised and written off over the life of the mine. Much expenditure, however, is often written-off on a straight line or reducing balance basis when installed ready for use (reflecting the situation depicted in Figure 5) – not requiring, for example, production to have commenced before write-off commences. And successful exploration expenditure, despite feeding into increased project value, invariably attracts immediate write-off.

Moreover, as with other deferred-cashflow projects, like forestry, horticulture, real estate developments and infrastructure projects, annual capital gains accruing as mining projects approach production are not included in assessable income.

Thus, the ideal income tax treatment of cash flow taxes applied before income tax on mining projects, and the ideal income tax treatment itself, are relegated to the realm of theoretical interest only.

In practice, having RRT payments deductible for income tax purposes is a simple, practical approach to take with less than perfect rent tax and income tax arrangements. The effect of commonly more generous write-off of capital expenditure relative to economic depreciation, on the one hand, may in fact offset to varying degrees the effect of simply including cash flow tax payments in the income tax base, on the other - as observed in the stylised mining project analysed here.



MISCONCEPTION 7: HEDGING SHOULD BE EXCLUDED FROM AN RRT

The correct treatment of hedging under an RRT is most clearly appreciated through use of a hypothetical project subject to an RRT.

Figure 7 is a cash flow diagram of a stylised crude oil project. Following success in early exploration drilling, the following certainty-equivalent cash flows (flows that would be accepted with certainty against more beneficial but risky outcomes) are used to assess the project's viability. Those developing the project want to include in this assessment hedging arrangements to 'lock-in' a forecast price of $80/bbl for crude oil (the current spot and futures price of crude oil). The cash flows therefore include brokerage costs associated with selling (going short) sufficient crude oil futures contracts at $80/bbl to cover the forecast 95m barrels of crude oil production in Years 2 to 4 (if only the risk of reductions in crude oil prices were to be hedged, options or options over futures contracts could be used instead of futures contracts). The brokerage costs for the futures contracts are put at $120m in Years 1 and 2, $70m in Year 3 and $25m in Year 4 covering a fixed price per contract when contracts are rolled over ever month (there are speculators on the other side of the contracts hoping the price of crude oil futures increases). Thus, the project's cash flows are:

Stylised crude oil project before RRT
FIGURE 7: Cash flows of crude oil project


Before RRT

Before RRT, the project's NPV is $2107 with discounting at 6% pa. This is confirmed in Table 12 (printout from the MyProject package).

Cash flow analysis of crude oil project before RRT

If a price for crude oil lower than $80/bbl were fed into the cash flow analysis, the same year-by-year cash flows as in Figure 7 and Table 12 would result (with the lower spot price and futures price spiking lower each time crude oil is sold at the end of Years 2, 3 and 4 for simplification purposes). That is because for every $1 lost on the actual sale of crude because price is lower than $80/bbl, the project developers would gain $1 on their futures contracts. Similarly, for prices above $80/bbl the cash flows would remain unchanged - though in that case the project developers would get more from the sale of crude but lose the same amount on their futures contracts.

After RRT

After the imposition on crude oil projects of an RRT with a threshold carry-forward rate for losses of 6% pa and a 40% RRT tax rate, the NPV of the project with the pre-RRT cash flows in Figures 7 and Table 12 is $1264 with discounting at 6% pa. That post-RRT result - reflecting a crude oil price of $80/bbl - is shown in Table 13. With threshold rate equal to discount rate, the post-RRT NPV is equal to the $2107 pre-RRT NPV reduced by the 40% tax rate percentage, or $2107x(1-0.4) - as expected from equation (2). $989m of RRT is paid.

Cash flow analysis of crude oil project after RRT

As before the RRT, if a price for crude oil lower or higher than $80/bbl were fed into the post-RRT cash flow analysis, the year-by-year post-RRT cash flows would be identical to those in Table 13 so long as:

If the hedging gains or losses are included in the consideration received by the developers for the sale of the project's crude oil (making them assessable and deductible, respectively), the proportional relationship shown in equation (2) will be maintained between the NPV of the project pre- and post-RRT. A price higher than $80/bbl would be offset dollar for dollar by losses on associated futures contracts and reductions in receipts due to a crude oil price below $80/bbl would be offset by hedging gains. The developers should make much the same decisions concerning the crude oil project - including whether to hedge the crude oil price or not - after the RRT as before.

If, however, hedging gains and losses were excluded from the RRT base, the pre-RRT NPV of the project would be reduced by less than the tax rate proportion by the RRT if crude oil prices were less than $80/bbl - because lower receipts from crude oil sales would be included in RRT assessment but the associated hedging gains would not be (though exclusion of brokerage costs would dampen this effect somewhat). Even though the developers had effectively locked in a fixed price for their crude they would be taxed under the RRT on less than this. Table 14 shows the project's post-RRT cash flow analysis assuming crude prices spike down to $60/bbl at sale time and excluding associated hedging gains as well as brokerage costs. The post-RRT NPV of actual cash flow (not cash flow for RRT purposes) is $1696m - shown in column (g) - compared to the post-RRT NPV of $1264m in Table 13. Rather than a neutral 40% reduction in pre-RRT NPV ($2107m from Table 12), the reduction is now only 19.5%. Moreover, instead of $989m of RRT being paid (Table 13), column (c) in the table shows only $486m is paid.

TABLE 14: Cash flows of crude oil project with price of crude at $60/bbl
YearNet receipts

(a)
$m
Capital
expenditure
(b)
$m
RRT payments

(c)
$m
Notional RRT
cash flow
(d)
$m
Excluded
brokerage costs
(e)
$m
Excluded
hedging gains
(f)
$m
Actual cash flow

(g)
$m
201002000-20000-200
2011010000-10001200-1120
20121400046.11353.91208002033.9
201311000440660707001290
20142005000-300(h)2540075
NPV @ 6%--410.5378--1696

Notes to table:

  1. Crude oil production of 40m bbl, 35m bbl and 20m bbl from 2012 to 2014 at $60/bbl (effects of hedging excluded).
  2. As in Table 13.
  3. RRT payments based on cash flows in columns (a) and (b).
  4. Column (a) less columns (b) and (c).
  5. Hedging brokerage costs excluded from RRT base.
  6. Hedging gains excluded from RRT base (crude oil production in year times $20/bbl) arising from futures contracts sold at a price of $80/bbl with prices falling to $60/bbl.
  7. Column (a) plus column (f) less columns (b), (c) and (e).
  8. Unrecouped RRT losses.

For prices higher than $80/bbl, the reverse of Table 14 would happen. The developers would be taxed on sales of crude for more than $80/bbl without being allowed deductions for associated hedging losses on the short futures contracts. The pre-RRT NPV of the project would be reduced by more than the tax rate proportion. Table 15 shows that the project's $2107m pre-RRT NPV would be reduced by 76.4% to $497m and $1886m of RRT (compared to the neutral $989m) would be paid.

TABLE 15: Cash flows of crude oil project with price of crude at $100/bbl
YearNet receipts
$m
Capital
expenditure
$m
RRT payments
$m
Notional RRT
cash flow
$m
Excluded
brokerage costs
$m
Excluded
hedging losses (a)
$m
Actual cash flow
(b)
$m
201002000-20000-200
2011010000-10001200-1120
201230000686.12313.91208001393
2013250001000150070700730
2014100050020030025400-125
NPV @ 6%--1608.72413--497

Notes to table:

  1. Losses (crude oil production in year times $20/bbl) arising from futures contracts sold at a price of $80/bbl with prices rising to $100/bbl.
  2. Net receipts less capital expenditure less RRT payments less excluded brokerage costs less excluded hedging losses.

The developers would see adverse effects from the RRT in their cash flow analyses at prices greater than $80/bbl and incentive effects from the RRT in their cash flow analyses at prices less than $80/bbl - a strange situation, distorting investment and operational decisions simply because RRT would be applied on the basis of a price for product that the producers of that product did not actually receive.

It would generally be expected that standard income tax arrangements would apply income tax to the income that the taxpayer actually received - in the case of our hypothetical project, on income from the sale of crude oil net of associated hedging gains or losses. RRT arrangements should be no different. Cash flows relating to borrowing/lending and capital raising aside, the recurrent net receipt flows underpinning the parameter R in equation (2) for activities subject to the RRT would generally have a direct parallel with income taxation provisions (though RRT would be expected to be on a cash, not an accrual, basis). As with income taxation, those subject to RRT should not be subject to tax on fictitious recurrent flows that are not what they actually receive or pay (while recognising the likely narrow basis of an RRT, possibly restricted to specified activities within ring-fenced projects). It is necessarily the C parameter in equation (2) where income tax write-off of capital expenditures often differs from the immediate expensing of an RRT.

Conclusions

The following conclusions can be drawn from the above analysis of hedging and RRT regimes.




© Copyright Wayne Mayo, May 2012